According to an update from the Jefferson County WI Government, the highway department will be resurfacing County Trunk Highway X from County Trunk Highway B to Air Park Drive. The work is scheduled to take place beginning the week of September 12, 2022. Some culverts will be replaced followed by the mill and overlay of the existing deteriorated asphalt pavement. During construction, the roadway will be closed to through traffic, but access will be maintained to local residences and businesses, as well as emergency vehicles. The road will remain closed until approximately the middle of October, depending on the weather. For questions, contact the Highway Department at (920) 674-7265.