Construction Updates Within the Burlington Area School District

In a post from the Burlington Area School District, they have discussed the recent updates occurring around the district. Over the past two weeks, work has been done at Cooper Elementary, Dyer Elementary, Waller Elementary, the District Office, and the High School radio tower. See more specific information below:

  • Cooper/Secured Entrance/Site work

  • Paint/Primer has been applied.

  • Tile work has begun in the office bathrooms.

  • Cabinets are being installed.

  • Site work is complete to grade.

  • Above ceiling rough ins for MEP's is ongoing.

  • Dyer/Montessori/Remodels/Roof

  • Paint/Primer has been applied.

  • Cabinets are being installed.

  • Carpet installation has started.

  • Above ceiling rough ins for MEPs is ongoing.

  • Roof is complete.

  • Waller/Secured Entrance/Bathrooms

  • Paint/Primer is being applied.

  • Tile work has begun in staff and student bathrooms.

  • Above ceiling rough ins for MEPs is ongoing.

  • 209 Building/District Office

  • Exterior C channel for the new windows is complete.

  • Interior metal studs is complete.

  • Rough in wall electrical has begun.

  • Exterior brick work continues.

  • BHS RadioTower/Asphalt

  • The new 24in I-beam to support the new tower has been installed.

  • Asphalt work on half of the parking lot in back is complete.

1 view0 comments

Recent Posts

See All

According to an update from the Elkhorn Police Department, sex offender Jason M. Deegan will be relocating to S. Wisconsin St. in Elkhorn on May 24. In 2002, Deegan was convicted of 2 counts of first

According to an update from the City of Lake Geneva, spring brush collection will end on May 27. Residents are reminded that all brush must be placed curbside by 6 a.m.

According to an update from the City of Watertown, at the Tuesday night Common Council meeting a group of firefighter/paramedics were honored for saving a life on scene. Awards went to Battalion Chie