Clinton Updates Progress Of School Construction

Last week, the Clinton Community School District shared updates on its facilities update project. The district says a new gym floor was installed at the Junior-Senior High School, electrical drops were installed for TechEd, multiple updates to its auxiliary gym including the curing of the floor and the concrete envelope being completely built, walls are completed for the team rooms, and breaker boxes have been installed. More information is posted to the Clinton Community School District on Facebook.