Clinton Community School District Shares Facilities Update Project Progress

The Clinton Community School District has shared progress with the facilities update project:


• Bathroom fixtures are going in the auxiliary gym.

• Acoustical panels are almost all installed.

• The TechEd & auxiliary gym additions are now painted.

• New air handlers were installed in both additions.

• Additions are now temperature controlled.

• TechEd classrooms are prepped and ready for new casework and doors to be installed.

• Landscaping is starting to be prepped for fall seeding.

• Footings are near completion at the 4K-6 building.

• Bids are in for our phase two capital maintenance roofing projects that will begin the spring of 2022.


0 views0 comments

Recent Posts

See All

In an update from the American College of Emergency Physicians, St. Mary's Hospital in Janesville has been named on their E-QUAL (Emergency Quality Network) Honor Roll as a national top performer in d

In a press release from the Rock County Medical Examiner’s office, they have released the name of an individual who passed away after a motor vehicle crash on Monday at about 4:50 p.m. on W. State Hig

According to an update from the Village of Johnson Creek, later today crews in the Southeast Neighborhood Utility Project area should be paving parts of Swap St. and South St. The village is remindin