Clinton Community School District Makes Progress Towards Facilities Update Project

According to an update from the Clinton Community School District, they have made progress toward the facilities update project. The Clinton Junior/Senior High School is almost completely finished, and they are now focusing on the 4k-6 grade project. The following was completed during week 33 of the project:


• 5th & 6th grade classrooms are getting new drywall installed.

• 5th & 6th grade locker areas are now constructed.

• HVAC duct work is being installed.

• New boiler room has new wider doors being installed.

• New water softeners and domestic water heaters are being installed.

• New sound proofing walls are being installed in the music room.


0 views0 comments

Recent Posts

See All

According to a press release from the City of Janesville, they have announced the appointment of Lieutenant Jamie Kessenich to the position of Deputy Fire Chief of the Janesville Fire Department, begi