According to an update from the Clinton Community School District, they have been continuing to make progress towards the facilities update project:
• Heavy demolition in phase 3 is being done.
• Kitchen renovation is underway.
• Cabinets and casework are going into the new addition classroom and common area.
• New lights are installed.
• The ceiling grid is near completion.
• Main AHU (Air Handling Unit) is installed.
• The Mechanical Room is nearing completion.
• Rear gym locker rooms are now painted.
• Restrooms are still being tiled.
• VCT flooring is starting to be installed in some of the available rooms.
• The old stage was removed from a classroom now making the room much larger.