Clinton Community School District Makes Progress Towards Facilities Update Project

According to an update from the Clinton Community School District, they have been continuing to make progress towards the facilities update project:


• Heavy demolition in phase 3 is being done.

• Kitchen renovation is underway.

• Cabinets and casework are going into the new addition classroom and common area.

• New lights are installed.

• The ceiling grid is near completion.

• Main AHU (Air Handling Unit) is installed.

• The Mechanical Room is nearing completion.

• Rear gym locker rooms are now painted.

• Restrooms are still being tiled.

• VCT flooring is starting to be installed in some of the available rooms.

• The old stage was removed from a classroom now making the room much larger.