According to an update from the Clinton Community School District, they have made the following progress towards the facilities update project:


• Painting took place in the front gym 4k-6.

• Windows are being sealed.

• Drywall is near completion in the 4K-5K addition.

• Flooring is being installed in the new additions restrooms.

• Demolition continues in Area B.

• Bathrooms are also being demolished and reconfigured.

• Library is under heavy construction this week.

• Tuckpointing is being done this week on the entire exterior of the 4K-6 building.


 
 
 