Clinton Community School District Makes Progress on Facilities Update Project

According to a post from the Clinton Community School District, they have been continuing to make progress on the facilities update project.


• New asphalt was recently laid

• New exhaust fans installed

• Most footings have been poured at the new 4K-6 school

• Gym continues to be painted; the ceiling is halfway done.

• Drywall and floors are now prepared for the new tile and bathroom fixtures that go in the new auxiliary gym.