City of Whitewater Gives Update on New Water Tower

wsld77

According to an update from the City of Whitewater regarding the new water tower, the steel structure has been completed along with the internal piping components. Painting crews will be onsite starting this week to paint the interior and exterior of the water tower over the next six weeks. Installation of electrical equipment and instrumentation will follow once painting is completed. Hydrotesting, disinfection, and cleanup will be completed nearing the end of the project. Completion is still on track for the end of September.