In an update from the City of Fort Atkinson, they have shared information on the water main replacement construction project. This week, water main installation is continuing on Adrian Boulevard, and water service lines are being installed on Gove Street. Binder course (lower layer) asphalt paving took place last Friday on Peterson Street, Grant Street, and Spry Street. Contractors are continuing to install new gas main, services, and meters on Spry Street and Grove Street. Coming up next week, water service lines will be installed on Gail Place and Adrian Boulevard, and water main installation on Maple Street will begin.