top of page

City of Fort Atkinson Shares Update on Water Main Replacement Project

According to an update from the City of Fort Atkinson regarding the water main replacement project, last week new water main installation began at the north end of Grove Street and progressed to the south. Peterson Street was constructed to subgrade and geogrid subgrade reinforcement was installed followed by crushed aggregate base course. Work this week includes new water installation to begin on Gail Place, and concrete sidewalk will be poured on Peterson Street. Preparation for curb and gutter replacement on Spry Street and Grant Street will continue.


1 view0 comments

Recent Posts

See All
bottom of page