Upcoming Work on County Highway P in Burlington

According to an update from the Town of Burlington, natural gas facilities along County Highway P (McHenry St) from South St. to Yahnke Rd. will be upgraded. Work will begin mid-April and be completed by early July. Traffic detours will be posted for motorists to follow as necessary. Access to local businesses and properties will remain open throughout the duration of the project, but may experience short-term interruptions as construction progresses. See the attachment below for more information.