According to an update from the City of Watertown WI Government, the city’s contractor will be performing pavement milling and asphalt overlaying this week. Today and tomorrow the following streets are scheduled for pavement to be milled:
• W. Spaulding Street – N. Church Street to the bridge over Silver Creek
• S. Twelfth Street – Sunset Avenue to Western Avenue (northbound traffic lane only)
• N. Fourth Street – Hill Street to the bridge over the Rock River
On October 7 and 9, streets are scheduled to be repaved, weather permitting. If you have any questions, please contact the Engineering Department at 920-262-4060.