Clinton Community School District Shares Updates on Facilities Update Project

The Clinton Community School District has shared the progress made during week 16 of their facilities update project.


• The Junior-Senior High School's new gym floor is now completed!

• Electrical drops are being installed in the TechEd addition

• Auxiliary gym floor is now poured and curing

• Auxiliary gym concrete envelope is completely built

• Walls are almost completed in the new team rooms

• Electrical conduits and breaker panel boxes are installed in the auxiliary gym mechanical mezzanine

• Approaches to the TechEd addition are being poured soon