top of page
wsld77

Clinton Community School District Moves Forward with Facilities Update Project

In a post from the Clinton Community School District, they have detailed more progress made towards the facilities update project. Read about their progress below:


• Doorway created for collaboration between Metals & Woods

• Electrical & Air drops installed in TechEd shops

• Concrete floorings being poured in SR/JR High School Team Rooms and TechEd additions

• Load bearing support beams are being installed in the wrestling room

• Phase 1 Capital Maintenance roofing project is completed on the SR/JR High School

• 90% of concrete walls are now installed on the Auxiliary Gym


1 view0 comments

Recent Posts

See All

Commenti


bottom of page