In an update from the Clinton Community School District, they have been continuing to make progress towards the facilities update project:
• New sample furniture was delivered to the Elementary School for teachers to see what is out there and to think about what will work best for all.
• Current Middle School, soon to be the new 4K-6 building, had heavy demolition going on last week.
• The New Auxiliary gym floor at CJSH is now sanded and is being prepped for staining and court markings.