Clinton Community School District Makes Progress Towards Facilities Update Project

Apr 1, 2022
1 min read

According to an update from the Clinton Community School District regarding the facilities update project, the following progress has been completed:


• Drywall is almost completely up in the new addition.

• Windows are also installed in the new addition.

• Mechanicals are still being installed.

• Air handling units and VAV boxes have arrived and are being installed.

• VCT tile is all down in the 5th & 6th grade wing.

•White boards, tack boards, TVs and Smart boards are currently being installed in the 5th & 6th grade wings.


 
 
 