top of page

Clinton Community School District Makes Progress Towards Facilities Update Project

According to an update from the Clinton Community School District, they are continuing to make progress towards the facilities update project:


• Rear gym floor is almost completed.

• Acoustical tiles going up in the new 4K-6 music room.

• New energy efficient led lights and ceiling tiles went up this week.

• New classroom door frames with sidelites being installed.

• The new 4K-5K addition continues to be wrapped with decorative stone and brick.

• 5th & 6th grade bathrooms are starting to get partitions installed in the toilet rooms as well as new tile work.

• Grounds crew has been working hard at building new benches for all of the baseball and softball dugouts.

1 view0 comments

Recent Posts

See All
bottom of page