According to an update from the Clinton Community School District, they are continuing to make progress towards the facilities update project:
• Rear gym floor is almost completed.
• Acoustical tiles going up in the new 4K-6 music room.
• New energy efficient led lights and ceiling tiles went up this week.
• New classroom door frames with sidelites being installed.
• The new 4K-5K addition continues to be wrapped with decorative stone and brick.
• 5th & 6th grade bathrooms are starting to get partitions installed in the toilet rooms as well as new tile work.
• Grounds crew has been working hard at building new benches for all of the baseball and softball dugouts.
Comments