According to an update from the Clinton Community School District, they are continuing to make progress towards the facilities update project:
• Old lockers are removed and new cubbies will be installed.
• HVAC ductwork is being installed in Area B.
• Plumbing work is being conducted.
• New door frames are being installed.
• New drywall is being installed in Area B as well as the new cafeteria.
• New HVAC univents are being installed.
• Old restrooms are being renovated.
• Old doorways are being infilled.
• New lights are being installed in the front gym.
• Old flooring was removed.
• New bathrooms are being tiled.
• The future new playground area is being cleared.
• The old boiler room is being decommissioned.
• New cubby areas are being built in the new addition.
• The old girls locker room is being renovated to be a new conference room.