Clinton Community School District Makes Progress on Facilities Update Project

Apr 15, 2022
1 min read

According to an update from the Clinton Community School District, they have been continuing to make progress towards the facilities update project:


• Drywall continues to be installed in the new addition.

• Exterior work is nearing completion on the addition.

• The team worked hard at work creating a game plan for Phase 2 area B finishes.

• Glass is being installed in the new cafeteria on the new addition.

• Demolition is being conducted in Area B.

• Old roofing deck is exposed.

• Work on updating the lighting began in the front gym of the current Middle School.

• Ceiling and lights are being updated in the current Middle School LMC.


 
 
 