Clinton Community School District Makes Progress on Facilities Update Project

wsld77

According to a post from the Clinton Community School District regarding the facilities update project:


• New curbs have been poured on Ogden Ave. as well as behind the new auxiliary gym

• Foundation on the new Elementary School is being dug out and footings are starting to be placed

• Auxiliary gym corridor has walls up now

• Auxiliary gym bathrooms walls are now framed as well as new door frames are installed

• Auxiliary gym roofing is 75% complete

• Auxiliary gym roof drains are being installed and the mezzanine roof is complete

• The Ag Shop is almost completely painted

• New auto shop has new auto exhaust fans installed


 
 
 