The Clinton Community School District has made progress on the facilities update project:
• The long-awaited roofing material (2 months late) finally arrived and was installed on the Tech Ed addition
• We had a groundbreaking ceremony at the 4K-6 school
• 4K-6 foundation excavation and underground utilities are underway.
• New conduits for fiber optic lines connecting the 4K-6 school to the bus barn were installed
• The high school gym locker room wall built out of block and steel studs were completed
• Wood doors and hardware arrived & will be installed next week at the high school