City of Fort Atkinson Provides Update on Bridge Project

According to an update from the City of Fort Atkinson regarding the Robert St. Bridge construction project, last week removal of the east and west parapet was completed, and excavation at the north abutment started Friday. Motorists traveling through the Riverside Dr. and Robert St. intersection should stay alert and watch for dump trucks exiting the site and hauling the old pavement away.


This week, removal of the main bridge deck will begin at the north end and progress to the south. This removal operation will move at a measured/deliberate pace with barges in a set location for long periods of time. Boat traffic should be alert while passing under the bridge, and steer clear of the barge and equipment. Roadway traffic patterns will remain as currently set for multiple weeks.


0 views0 comments

Recent Posts

See All

According to the daily media report from the Beloit Police Department, they are looking for a suspect in connection to a trespassing case that was reported yesterday at about 7 a.m. on Maple Ave. The

According to an update from Watertown’s Mayor, Emily McFarland, Watertown was selected for a State Main Street Grant for a parking study in the downtown area. Parking study options will be presented