City of Burlington Provides Update on Jefferson Street Project

The City of Burlington has provided an update on the Jefferson St. project. On the west side of the bridge, outdoor lighting work will occur this Thursday and Friday. Concrete work, including sidewalks, driveway aprons, etc. will also occur this week. Pavement grading is scheduled for Monday, October 24, and paving will occur on Wednesday, October 26. Landscaping and restoration work will soon be scheduled and is determined based on the weather.