The Burlington Area School District has given more updates towards construction projects being completed throughout the district. See the updates below:
209 Building/District Office
Overhead inspections of MEP's was completed, ceiling tiles have been installed.
Boardroom accent wall is complete.
Interior carpet is complete.
Interior doors are scheduled to arrive next week to be installed.
Plumbers will install the new fixtures next week.
Casework will start next week.
Exterior metal panel work is expected to be finished next week.
Site work is schedule for middle of October.
Wainwright/Karcher site
Old Karcher and all building footing and concrete have been removed.
Pulverization of old building contents has finished and the rest of the material has been hauled off.
Site work will begin next week to construct the new football and soccer field
Commenti