According to a press release from the Village of Johnson Creek regarding the Southeast Neighborhood Utility Reconstruction Project, next week on Monday crews will be on site grading sidewalks and setting up stringline on S. Watertown St. and Clarke St. Then, on Tuesday, they will begin pouring the sidewalks. Crews will be on-site throughout the entirety of the week to work on topsoil restoration.