According to an update from the Walworth County Sheriff’s Office, resurfacing work on County Trunk Highway B from Castle Terrace Ave. to Linton Rd. along the south Village of Fontana Limit will begin the week on April 25 through mid-July. Project improvements include replacement of highway cross culverts and driveway culverts, installation of new curb and gutter at intersection corners, partial-depth asphalt pavement milling, and construction of new asphalt pavement surface. During construction, the highway will remain open to traffic and utilize single-lane closures with flaggers. The roadway will be reopened to two-way traffic at the end of each day. Access will be maintained at all times for emergency services, postal delivery, garbage collection, and school buses. For questions on the project, call the Walworth County Public Works Department at (262)741-3114.