Maryland Reconstruction Project in Burlington

In a post from the City of Burlington, WI, they have shared updates to the Maryland Reconstruction project. This week, crews are expected to continue water main relay work, and move existing hydrants at station 22 and 60 and replace hydrants at station 26 and 75. This will tentatively be tomorrow, and water will need to be turned off during this work. Notices will be handed out in advance. Crews will also begin sanitary sewer work at Congress Street while watermain is waiting for safe sample & pressure test results.