Construction Update at Karcher Middle School in Burlington
In a post from the Burlington Area School District, they gave updates on the construction at Karcher Middle School. The exterior metal panels are about 75% complete, and the music suite, tile work in lower areas, stairs in the commons, and elevator installation is completed. Crews are currently still working on painting and installing doors, interior glass, and hardware. Gym wood flooring will begin in February, and plumbing fixtures will be installed next week.