top of page

Clinton Community School District Shares Progress Towards Facilities Update Project

In an update from the Clinton Community School District, they have shared the progress made towards the facilities update project:


• Interior paint and ceiling grid work

• Music room ceiling grid and ductwork

• Phase 2 ceiling removal, electrical and pipe installed

• Erected canopy steel and deck

• Completed cafeteria roof deck

• Weather barrier and precast installed

• Addition ductwork plumbing and temporary lighting installed

• Addition classroom stud framing and plumbing


0 views0 comments

Recent Posts

See All

Comments


bottom of page