Clinton Community School District Shares Progress Towards Facilities Update Project
- wsld77
- Feb 21, 2022
- 1 min read
In an update from the Clinton Community School District, they have shared the progress made towards the facilities update project:
• Interior paint and ceiling grid work
• Music room ceiling grid and ductwork
• Phase 2 ceiling removal, electrical and pipe installed
• Erected canopy steel and deck
• Completed cafeteria roof deck
• Weather barrier and precast installed
• Addition ductwork plumbing and temporary lighting installed
• Addition classroom stud framing and plumbing
Comments