Clinton Community School District Shares Progress Towards Facilities Update Project

In an update from the Clinton Community School District, they have shared the progress made towards the facilities update project:


• Interior paint and ceiling grid work

• Music room ceiling grid and ductwork

• Phase 2 ceiling removal, electrical and pipe installed

• Erected canopy steel and deck

• Completed cafeteria roof deck

• Weather barrier and precast installed

• Addition ductwork plumbing and temporary lighting installed

• Addition classroom stud framing and plumbing


 
 
 