According to a post from the Clinton Community School District, the facilities update project has been continually making progress. See the updates below:
• Room 109A entrance has been built waiting for modular wall to arrive for installation
• Walls are going up for the Auxiliary Gym vestibule
• Main Gymnasium Maple floor is starting to be installed
• Vestibule connecting the current HS Wrestling room to the new Auxiliary Gym was created this week.
• Birds Eye view of the construction progress on the Auxiliary Gymnasium
• Phase 1 roof replacement of the Jr.-Sr. High School on schedule and moving along nicely
• Base flooring in TechEd is prepped and ready to pour concrete scheduled for August 6th
• Steel has arrived on the job site
• Ag classroom has been expanded and wall is now up