City of Fort Atkinson Shares Update on Water Main Replacement Project

According to an update from the City of Fort Atkinson regarding the water main replacement project, the contractor has tied into the existing water main at Grove and Hilltop, and Adrian and Hilltop. They installed six water main valves at these intersections. They’ve installed sanitary sewer on Adrian. All water service lines on Gail Place are installed, and all but one water service line are installed on Grove Street.


Next week they’ll finish water main on Adrian Blvd., and begin water service lines on Adrian Blvd. Landscaping will begin on Peterson Street. The next phase of the concrete curb and gutter, sidewalk, and driveway may begin later next week as well.


0 views0 comments

Recent Posts

See All

According to an update from Racine County Parks, the new kayak and canoe launch at Case Eagle Park in Burlington is officially open to the public. Park staff is still wrapping up the project with som

In an update from the City of Elkhorn, they noted that some residents may have received a letter from Hydro-Corp saying that their water meter needs to be changed out. If you receive this letter, cal

bottom of page