According to an update from the City of Fort Atkinson regarding the Robert St. Bridge, the bridge parapet removal is complete and the deck is currently being removed. Deck removal is in the north span currently, and progressing to the south. Boat traffic should be alert while passing under the bridge and steer clear of the barge and equipment. Work on the north abutment is moving forward and rebar will be placed this week. The first concrete pour is scheduled in two weeks.